Completing GEPA Evaluations
The Georgia Environmental Policy Act (GEPA) is a state law designed to help state agencies conduct their projects “with an awareness that they are stewards of air, land, water, plants, animals and environmental, historical and cultural resources.” For the Board of Regents (BOR), this is accomplished by completing environmental evaluations of each project or “proposed government action” as prescribed by the Act.
Many BOR new construction and renovation projects meet the definition of a “proposed government action” under state law, and therefore require a GEPA evaluation. Significant legal liability and fines/penalties could result from failure to complete a GEPA evaluation or from inaccurate or incomplete GEPA evaluations.
The following procedures shall be used by design professionals and USG institutions to ensure compliance with GEPA:
For Major Capital Projects:
The project design professional shall retain a qualified environmental consultant to complete the GEPA evaluation during the schematic design phase of the project. The design professional shall review and consider the findings of the environmental site assessment (ESA) report (which should have been completed during programming/site selection or pre-planning phase of the project - see the BOR Procedure for ESA’s Criteria for Environmental Site Assessments. The ESA report should provide the environmental consultant with the technical site information necessary to properly complete the GEPA evaluation. If an ESA was not completed during programming/site selection or pre-planning, the environmental consultant shall be commissioned to complete a “combined ESA/GEPA evaluation” (see Appendix 6 D of the BOR Building Project Procedures Manual) at this time. The completed GEPA evaluation (or the combined ESA/GEPA report) shall be submitted to the BOR Program Manager in a timely fashion during schematic design or the initial stages of preliminary design to obtain the necessary approvals. If the GEPA evaluation determines that no adverse effects will be created by the project, the GEPA evaluation shall be approved and the project may proceed as planned. If the GEPA evaluation determines there will be adverse effects, the project design shall either be modified to mitigate the adverse effects, or an environmental effects report (EER) shall be prepared in accordance with the attached GEPA Implementation Procedure. Note: Preliminary design documents shall not be approved without an approved GEPA evaluation.
For Minor Capital Projects:
In most cases, the project design professional shall retain a qualified environmental consultant to complete the GEPA evaluation during the schematic design phase of the project. For certain minor capital projects where it is believed that an enironmental consultant may not be necessary, the project design professional shall contact the BOR Program Manager and/or the BOR Program Manager for Environmental & Occupational Safety during schematic design to discuss options for completing the GEPA evaluation. For certain minor capital projects, the design professional and/or the institution’s representative(s) may have adequate knowledge of the subject property, and the project may be such that hiring an environmental consultant may not be necessary. If the decision is made to retain an environmental consultant, all procedures outlined above (under “major capital projects) shall be followed. If an environmental consultant is not retained, the design professional shall consult with the institution representative(s) and shall complete the GEPA evaluation themselves. The completed GEPA evaluation (or the combined GEPA/EAS report) shall be submitted to the BOR Program Manager in a timely fashion during schematic design or the initial stages of preliminary design to obtain the necessary approvals. If the GEPA evaluation determines that no adverse effects will be created by the project, the GEPA evaluation shall be approved and the project may proceed as planned. If the GEPA evaluation determines there will be adverse effects, the design plans shall be altered to mitigate the effects or an environmental effects report (EER) shall be prepared in accordance with the attached GEPA Implementation Procedure. Note: Preliminary design documents shall not be approved without an approved GEPA evaluation.
All Projects that are not Major or Minor Capital Projects:
The design professional and/or the institution shall be responsible for completing the necessary GEPA evaluation (as outlined above under major or minor capital projects) for any project within the University System of Georgia which may be defined as a “proposed government action” in accordance with the attached GEPA Implementation Procedure. For proposed projects where questions may exist, institutions and design professionals are instructed to consult with their BOR Program Manager and/or the BOR Program Manager for Environmental & Occupational Safety. Note: Preliminary design documents shall not be approved without an approved GEPA evaluation.
Georgia Environmental Policy Act (GEPA) - Board of Regents’ Implementation Procedure
- INTRODUCTION
GEPA Evaluations shall be completed for all USG “proposed government actions” so that appropriate decisions may be made as to whether to proceed with a particular project or whether to modify a project design in some way. GEPA evaluations shall be completed during schematic design or during the initial phase of preliminary design. If the GEPA evaluation identifies any possible significant adverse effects, an environmental effects report (EER) shall be prepared in accordance with GEPA before the project may proceed any further. The Vice Chancellor for Facilities shall, upon review of the GEPA evaluation and other relevant information, determine whether a project may proceed as planned, whether design changes are necessary, or whether an environmental effects report (EER) must be completed. - PROJECT QUALIFICATION CRITERIA
The first decision under GEPA is to determine whether a proposed project or action qualifies as a “Proposed Governmental Action” and therefore must be evaluated in accordance to GEPA. USG projects qualify for GEPA if:- The action (project) is funded by state funds, and if so funded, then any one action below mandates an assessment:
- The action is a land disturbing activity, including but not limited to: scraping, plowing, clearing, dredging, grading, excavating, transporting or filling of land, or placement of any structure or impervious surface, dam, obstruction or deposit.
- The moving or altering of any structure on or eligible for placement on the Georgia Register of Historical Places.
- The sale or exchange of more than five acres of state owned land.
- The harvesting of five acres or more of trees over two inches in diameter at breast height.
- THE FORMS
Project designers and institutions shall use the attached GEPA Checklist and Project Initial Evaluation forms to complete the GEPA Evaluation.
- RESULTS
Projects or actions determined by the Vice Chancellor or designated official as not having a significant adverse effect on the environment shall require no further action.
Projects or actions determined by the Vice Chancellor or designated official as having possible adverse effect on the environment shall have further action.
For projects with possible adverse effects, the affected institution shall authorize the preparation of an EER by a qualified professional, including but not limited to, a discussion of:
- The environmental impact of the proposed governmental action;
- Alternatives to the proposed project action, including no action;
- Any adverse environmental effects which cannot be avoided if the proposed project or action is undertaken;
- Mitigation measures proposed to avoid or minimize the adverse impact of the Proposed project or action;
- The relationship between the value of the short-term uses of the environment involved in the proposed project or action and the maintenance and enhancement of its long-term value;
- The effect of the proposed project or action on the quality and quantity of water supply;
- The effect of the proposed project or action on energy use or energy projection.
- Any beneficial aspects of the proposed project or action, both short-term and long-term, and its economic advantages and disadvantages; and
- Comments from other governmental agencies which may have jurisdiction, special expertise, or other interests in regard to any category noted on the Environmental Check List as producing possible adverse environmental effects (written correspondence shall be attached).
The institution will provide electronic copies of the EER and related document to the system office.
At least 45 days prior to the project bid date, the affected institution shall publish a notice in the legal organ of the county in which the proposed project or action (or any part thereof) is to occur stating that an EER has been prepared. The institution shall provide a copy of the EER (including other governmental agency comments) to the Director of the Georgia Environmental Protection Division and to the BOR Office of Real Estate and Facilities. The institution shall also make the EER available to the public and to counties, municipalities, institutions, and individuals, upon request (eg. public library).
If the institution receives, within 30 days of the publication of the notice, at least 25 written requests for a public hearing, the responsible institutional designee (eg. Facilities Director or other senior administrator) shall hold a public hearing in accordance with the provisions of GEPA.
The institution shall consider the EER and all comments received either in writing or during the public hearings, if held. After considering these comments, the institution shall decide whether to proceed with the project or action as originally proposed, to proceed with changes, or not to proceed. Notice of the decision shall be given in writing to the Vice Chancellor of Real Estate & Facilities, the Director of the Georgia Environmental Protection Division, a representative of the Georgia Historic Preservation Division, and published in the legal organ of the county in which the project or action (or any part thereof) is to occur.
The decision of the institution to proceed shall not create a cause of action in any person, corporation, association, county or municipal corporation except as provided by law regarding the procedure of giving notice of publication of the EER and the decision.